Tag Archives: Mesa Power

Nuclear v Wind: The Answer is Blowin’ In The Wind.

Back in May, Rebecca Smith reported in the Wall St. Journal (click here for Popular Logistics posting) that Florida Power & Light wants to spend $12 to $18 Billion to build a 2.2 GW or 3.0 GW nuclear plant at the aptly named “Turkey Point” facility. At about the same time, Reuters reported that T. Boone Pickens ( click here for Popular Logistics posting ) – who made his money in oil – is building a 4 GW wind farm for $10 Billion. FPL says the nuclear plants may be finished by 2020. Pickens says Phase 1 of the wind farm – a 1 GW installation – will be complete by 2011. CNN has also picked up the story .

Nuclear power requires fuel. The fuel cycle produces greenhouse gases. Nuclear power operations produce tons of radioactive waste. Wind power requires no fuel and produces no waste.

On the one hand – $6 per watt, 10 to 12 years to build, tremendous amounts of extremely hazardous wastes. On the other hand $2 per watt, 3 years to build, no waste.